Ganga Expressway: Route Map, Key Cities & Current Status

The Ganga Expressway, the longest expressway in Uttar Pradesh so far, was inaugurated by Prime Minister Narendra Modi on Wednesday, 29 April 2026. It is a 6-lane, expandable up to 8-lane, greenfield expressway connecting western Uttar Pradesh to eastern Uttar Pradesh in India.
The total length of the Ganga Expressway is 1,049 km (652 miles). It consists of two phases: the completed Phase 1 (Meerut–Prayagraj), which is 594 km (369 miles) long, with its western end at Bijauli village in Meerut district and eastern end at Judapur Dandu village in Prayagraj district; and the under-construction Phase 2 (455 km / 283 miles), which includes two extensions—Spur 1 (Upper Ganges Canal Expressway), a 110 km route from Bulandshahr–Meerut to Haridwar in the west, and Spur 2, a 314 km Prayagraj–Ballia Expressway route in the east.
Some of the major intersections on this expressway include Meerut, Kanpur, and Prayagraj in Phase 1, and Haridwar, Varanasi, and Ballia in Phase 2. Major cities along the route include Muzaffarnagar, Haridwar, Bijnor, Meerut, Hapur, Bulandshahr, Sambhal, Budaun, Bareilly, Shahjahanpur, Hardoi, Kanpur, Raebareli, Pratapgarh, Prayagraj, Mirzapur, Varanasi, and Ballia.
History of Ganga Expressway
2007: Conception
In 2007, the Ganga Expressway was initially proposed by Uttar Pradesh Chief Minister Mayawati as the Greater Noida–Ballia Expressway, but the project was delayed.
2019: Project Revived
In 2017, Uttar Pradesh got a new Chief Minister, Yogi Adityanath. The project was revived, and the first installment of ₹2,000 crore was allocated in 2020 for the construction of Phase 1. The Uttar Pradesh Expressways Industrial Development Authority is the government agency responsible for project development.
2019–2026: Phase 1 Construction Started
The total expected project cost in 2021 was ₹37,350 crore, including land acquisition costs of around ₹9,500 crore. Land acquisition began in 2019 and was largely completed by 2021.
In 2021, environmental clearance was obtained from the Ministry of Environment, Forest and Climate Change, and the Uttar Pradesh Cabinet approved a ₹36,230 crore budget for construction. On 18 December 2021, after Prime Minister Narendra Modi laid the foundation stone in Shahjahanpur, construction work began in April 2022.
UPEIDA divided Phase 1 into 12 construction packages under the Design-Build-Finance-Operate-Transfer (DBFOT) model. The first 129.6 km stretch, from Bijauli (Meerut) to Nagla Baraha (Budaun), was constructed by IRB Infrastructure Developers, while the remaining 464.2 km, from Nagla Baraha (Budaun) to Judapur Dandu (Prayagraj), was constructed by Adani Enterprises.
Economic Use
Ganga Industrial Corridor
The area along the Ganga Expressway is being developed as an industrial corridor. New industries are emerging around Meerut, Budaun, Kanpur, Varanasi, and Prayagraj. The government is also planning to set up pharma parks, textile parks, and IT parks along the expressway.
In Meerut, the Uttar Pradesh government acquired land in 2023 to develop an industrial city near the expressway’s entry and exit points. Kanpur, after the completion of both phases, will serve as a major economic and industrial hub, as it will be the central point of the expressway, with multiple projects planned in the Agra-Lucknow Expressway and Awadh Expressway regions.
Military Airstrip
Sections of the Ganga Expressway have been developed to function as emergency airstrips for the Indian military. Indian Air Force fighter jets and transport aircraft conducted landing and take-off drills on 2 May 2025 on a 3.5 km (2.2 miles) emergency landing facility near Shahjahanpur. Aircraft involved included Su-30MKI, Mirage 2000, MiG-29, Jaguar, C-130J Super Hercules, An-32, and the Mi-17 V5 helicopter.
Current Status of Ganga Expressway
Phase 1: Meerut–Prayagraj
The Ganga Expressway project, first proposed in 2007, was revived and officially relaunched by Chief Minister Yogi Adityanath on 29 January 2019. The expressway is planned to run broadly parallel to the Ganga River while maintaining a 10 km distance to meet environmental norms.
By 2020, ₹2,000 crore had been allocated, and land acquisition progressed rapidly through 2021, reaching over 90% completion by August. The project received environmental clearance in November 2021, and Prime Minister Narendra Modi laid the foundation stone on 18 December 2021. Contracts were awarded to Adani Enterprises and IRB Infrastructure, and physical construction began in April 2022.
By late 2023, major groundwork—including clearing, grubbing, and initial earthworks—was largely completed. The Uttar Pradesh government also announced the development of an industrial city near Meerut along the expressway.
Prime Minister Narendra Modi inaugurated the expressway on 29 April 2026. Following its inauguration, the Uttar Pradesh government is planning to develop industrial hubs along the route under a hub-and-spoke model.
Phase 2
Phase 2 includes two spur routes. Spur 1 (Meerut–Haridwar) received a ₹50 crore allocation in February 2025 for pre-construction activities. Spur 2 (Prayagraj–Ballia) remains in the pre-construction stage, with surveys completed by UPEIDA in 2024 and preparatory work ongoing as of August 2025.
Frequently Asked Questions
Q1. What is the Total Length of the Ganga Expressway?The total length of the Ganga Expressway is 1,049 km (652 miles). Phase 1 from Meerut to Prayagraj is 594 km and is already completed. Phase 2 is 455 km and still under construction, which includes Spur 1 from Meerut to Haridwar (110 km) and Spur 2 from Prayagraj to Ballia (314 km).
Q2. What is the Estimated Cost of the Ganga Expressway?
The total expected cost of the Ganga Expressway is ₹37,350 crore. The construction cost approved by the Uttar Pradesh Cabinet is ₹36,230 crore and the land acquisition cost is approximately ₹9,500 crore. The project is executed by UPEIDA under the DBFOT model.
Q3. Which Major Cities Does the Ganga Expressway Connect?
The Ganga Expressway passes through 12 major districts of Uttar Pradesh. Phase 1 connects Meerut, Hapur, Bulandshahr, Sambhal, Budaun, Shahjahanpur, Hardoi, Unnao, Raebareli, Pratapgarh and Prayagraj. Phase 2 will further connect Haridwar, Varanasi and Ballia.
Q4. What is the Impact of the Ganga Expressway on Uttar Pradesh?
The Ganga Expressway is creating a huge positive impact on Uttar Pradesh. The area along the route is being developed as an industrial corridor with new industries, pharma parks, textile parks and IT parks coming up in Meerut, Budaun, Kanpur, Varanasi and Prayagraj. In 2023, the UP government acquired land in Meerut to develop an industrial city near the expressway. After both phases are complete, Kanpur will become the central economic hub of the expressway. It also has a 3.5 km emergency airstrip near Shahjahanpur for Indian Air Force use.
Q5. What is the Current Status of the Ganga Expressway?
Phase 1 of the Ganga Expressway was officially inaugurated by Prime Minister Narendra Modi on 29 April 2026 and is now fully open for public use. Phase 2 is currently in the pre-construction stage. Spur 1 from Meerut to Haridwar received a ₹50 crore budget allocation in February 2025 and Spur 2 from Prayagraj to Ballia has completed its surveys with preparatory work ongoing.
Q6. What are the start and end points of the Ganga Expressway?
The Ganga Expressway start and end point begins from Bijauli village in Meerut district and ends at Judapur Dandu village in Prayagraj district. The route of Ganga Expressway runs west to east, staying broadly parallel to the Ganga River at a 10 km distance to meet environmental norms.
Q7. Is Ganga Expressway central or state government, and who owns it?
Ganga Expressway is a state government project, not under NHAI or the central government. Ganga Expressway is owned by UPEIDA, the Uttar Pradesh Expressways Industrial Development Authority. IRB Infrastructure built the Meerut to Budaun section and Adani Enterprises built the Budaun to Prayagraj section under the DBFOT model.
Q8. What is the Ganga Expressway Route Map from Meerut to Prayagraj?
The Ganga Expressway route map Meerut to Prayagraj covers 594 km across 12 districts. It starts at Bijauli village in Meerut and ends at Judapur Dandu in Prayagraj, passing through Hapur, Bulandshahr, Sambhal, Budaun, Shahjahanpur, Hardoi, Unnao, and Raebareli. For a full size Ganga Expressway map with district markings and interchange locations, you can check our site.
Q9. What is the Ganga Expressway route in Varanasi, is it accessible now?
Varanasi is not on the current Phase 1 route. The Ganga Expressway route map in Varanasi falls under Phase 2, specifically the 314 km Ganga Expressway Prayagraj to Ballia route that passes through Varanasi. UPEIDA completed surveys for this section in 2024 and preparatory work is currently ongoing.
Q10. What Does the Ganga Expressway Phase 2 Route Map Cover?
The Ganga Expressway Phase 2 route map covers two spur routes. Spur 1 is the 110 km Upper Ganges Canal Expressway from Meerut toward Haridwar. Spur 2 is the 314 km Prayagraj to Ballia expressway route passing through Varanasi. For the detailed Ganga Expressway Phase 2 Prayagraj to Ballia route map, you can check our site.
Q11. What industrial areas are planned along the Ganga Expressway corridor?
The Ganga Expressway industrial area development is central to the project's economic vision. Pharma parks, textile parks, and IT parks are coming up near Meerut, Budaun, Kanpur, Varanasi, and Prayagraj. In 2023, the UP government acquired land near the Ganga Expressway entry exit points in Meerut to build a dedicated industrial city. After both phases are complete, Kanpur will be the central industrial hub sitting at the midpoint of the full 1,049 km route.
Q12. Which Two Cities Does Ganga Expressway Connect, and What is its Direction?
Ganga Expressway connects Meerut in western Uttar Pradesh to Prayagraj in central Uttar Pradesh in its completed Phase 1. The Ganga Expressway direction runs west to east. Once Phase 2 is complete, it will further connect Haridwar in the north to Ballia in the east, passing through Varanasi and making it one of the longest expressway corridors in India.
Q13. Can Ganga Expressway Be Used as a Prayagraj to Delhi Expressway Route?
Yes, Ganga Expressway runs from Meerut to Prayagraj. At the Meerut end, it connects seamlessly to the Delhi-Meerut Expressway, creating a continuous high-speed corridor from Prayagraj to Delhi without passing through any city centre.
Q14. Does Ganga Expressway Pass Through Bijnor, and Where on the Route Map?
Yes, Bijnor is one of the major cities along the Ganga Expressway Bijnor route map section near Meerut in the early stretch of Phase 1. For the exact Ganga Expressway Bijnor route map showing alignment through this district, you can check our site.